Home / NEBOSH IGC / Scenario practice / Cement works shutdown incident
Practice for NEBOSH IGC unit GIC1. 8 tasks, 100 marks.
You are a health and safety manager who has just joined Eastgate Cement Works (Eastgate). The site makes cement from limestone and clay. Raw material is ground, heated in a tall preheater tower and a rotating kiln, cooled, ground again and packed into bags or loaded into bulk tankers. Eastgate has 280 permanent employees working in three shifts. Once a year the kiln is shut down for 12 days for repair and maintenance. During the shutdown about 150 contractor workers join the site, working long hours in two shifts. The plant manager (PM) leads the site and reports to a head office in another city. The head of maintenance (HoM) runs the shutdown.
During the shutdown the preheater tower is cleaned and repaired. This involves work at height on open steel platforms, hot work such as cutting and welding, work inside vessels and ducts, and work on electrical systems and motors that must be isolated. A lost day of production costs Eastgate a large sum, and head office pays the PM a bonus if the shutdown finishes early. The PM has told the HoM that every extra day is "money thrown away". Shutdown contractors are paid a bonus for finishing tasks ahead of schedule.
Eastgate hires most of its shutdown contractors by asking for quotes and choosing the lowest. Two years ago the lowest quote for the preheater work came from a small firm, Delta Industrial Services (Delta), which has since been used every year. Nobody has checked Delta's safety record or insurance since the first year. Delta's workers get a 15 minute talk on the first day from a security officer, in English, although many of them speak mainly another language. Delta's supervisor says he has asked for a site safety contact but the HoM has told him that everyone is too busy.
Eastgate uses a permit to work system for hot work, work in confined spaces and work on isolated plant. Permits are written on paper forms. Supporting document 1 is an extract from the permit register for the shutdown. To save time, shift supervisors have been signing several permits at the start of each shift. The isolation of motors and feeders is done by electricians who attach a tag to each switch, but locks are not used because there are not enough of them. A gas test is supposed to be done before anyone goes inside a vessel, but the single gas detector is often needed elsewhere.
Eastgate has an emergency plan, last updated six years ago. It was written for normal operations. There is an alarm siren, but during the shutdown the noise from grinders and compressors often hides it. The site clinic has one nurse on the day shift only. The nearest hospital is 40 minutes away by road. During the shutdown the main access road is partly closed for crane work. Eastgate has never tested a rescue from the preheater tower.
Workers at Eastgate say that safety rules are "for the auditors". Permanent staff say that if they stop a job to ask a question, they are told that the schedule cannot slip. Delta workers say they do not report minor injuries or near misses because they believe Delta will be dismissed, and they fear losing wages. Meetings about safety stopped when shutdown planning began three months ago.
On day 8 of the shutdown, at about 02:30, a Delta worker was sent to clear a blockage in a cyclone in the preheater tower. He was working from an open platform, 35 metres above the ground, alone, because the others had been moved to another task to catch up on schedule. The permit for the job had been signed by the shift supervisor on the previous afternoon, and the box for isolation of the feed system was ticked but not checked. When the worker opened an inspection door, hot material built up behind the blockage poured out. He suffered serious burns to his arms and chest and fell back against a handrail. A colleague on the platform below heard him shouting, and it took 25 minutes to lower him to the ground because there were no rescue arrangements for the tower. The nurse was not on shift, a first aid box on the platform was empty, and the ambulance was delayed by the road closure. The PM has told the HoM that the incident must not delay the restart of the kiln.
Kept in the HoM's office. Reviewed by: nobody recorded.
| Permit | Work | Issued and accepted | Checks recorded | Closed |
|---|---|---|---|---|
| P-114 | Hot work, preheater level 4 | Same person signed both | Gas test not recorded | Not closed |
| P-118 | Entry to cooler duct | Issued 06:00, accepted 06:05 | Gas test recorded as done at 05:30, before the permit | Closed 15:00 |
| P-121 | Replace motor on feed system | Signed by supervisor, shift not shown | Isolation: tag only | Closed, no time |
| P-124 | Clear blockage, cyclone 3 | Signed day 7, 15:10, for use on night shift | Isolation box ticked, point not named | Open |
| P-126 | Scaffold erection, level 6 | Signed in blank for three days | No inspection by a competent person recorded | Not closed |
Explain the weaknesses in the way Eastgate selected and managed its shutdown contractors. (12)
Note: You should support your answer using relevant information from the scenario.
0 words
Tick each point that your answer made clearly and only once. Points here are this site's own. A real examiner may accept other valid points.
Marks counted: 0 of 12
Using supporting document 1 and the scenario, outline the weaknesses in the permit to work system at Eastgate. (14)
Note: Your answer must be based on the scenario and supporting document 1.
0 words
Tick each point that your answer made clearly and only once. Points here are this site's own. A real examiner may accept other valid points.
Marks counted: 0 of 14
Outline what a safe system of work for clearing a blockage in the preheater cyclone should include, and how Eastgate should develop and monitor it. (10)
Note: You should support your answer, where applicable, using relevant information from the scenario.
0 words
Tick each point that your answer made clearly and only once. Points here are this site's own. A real examiner may accept other valid points.
Marks counted: 0 of 10
(a) What immediate actions should Eastgate take after the incident? (b) What information should the investigation collect, and what underlying causes should it look for? (12)
Note: You should support your answer, where applicable, using relevant information from the scenario.
0 words
Tick each point that your answer made clearly and only once. Points here are this site's own. A real examiner may accept other valid points.
Marks counted: 0 of 12
Identify the weaknesses in Eastgate's emergency arrangements and first aid during the shutdown. (12)
Note: You should support your answer using relevant information from the scenario.
0 words
Tick each point that your answer made clearly and only once. Points here are this site's own. A real examiner may accept other valid points.
Marks counted: 0 of 12
Describe the organisational, job and individual factors at Eastgate that are likely to have contributed to the incident. (14)
Note: You should support your answer using relevant information from the scenario.
0 words
Tick each point that your answer made clearly and only once. Points here are this site's own. A real examiner may accept other valid points.
Marks counted: 0 of 14
Suggest how Eastgate could improve its active monitoring during the next shutdown, including leading indicators it could use. (12)
Note: You should support your answer, where applicable, using relevant information from the scenario.
0 words
Tick each point that your answer made clearly and only once. Points here are this site's own. A real examiner may accept other valid points.
Marks counted: 0 of 12
Using the stages Plan, Do, Check and Act, how could Eastgate improve its health and safety management of shutdowns, and what should top management do to show commitment? (14)
Note: You should support your answer, where applicable, using relevant information from the scenario.
0 words
Tick each point that your answer made clearly and only once. Points here are this site's own. A real examiner may accept other valid points.
Marks counted: 0 of 14
Marks counted across all tasks: 0 of 100. The real paper totals 100 marks.