ACCA · Performance Management · 16 questions
Name: ____________________ Date: ____________
A product mix is 2 units of A (contribution $8) to 1 unit of B (contribution $12). Fixed costs are $56,000. What are the total break-even units for the mix?
Product X earns $12 contribution using 2 hours of the scarce resource and product Y earns $15 using 3 hours. Which should be made first?
With two or more scarce resources, the best production plan is usually found by:
What is the shadow price of a scarce resource?
A 4 percent rise in price cuts quantity demanded by 10 percent. What is the price elasticity of demand?
Profit is maximised where:
Demand is P = 100 - 0.02Q and marginal cost is $20. What is the profit-maximising price?
A new product is launched at a high price which is later lowered. This is:
A division is at full capacity. The marginal cost of an item is $14 and it can be sold outside for $22. What is the minimum transfer price?
A company has spare capacity and receives a special order. Which costs are relevant?
Payoffs for three plans in a good, medium and poor market are A: 120, 80, 20; B: 90, 70, 50; C: 60, 60, 60. Which plan does maximin choose?
Using the same payoffs (A: 120, 80, 20; B: 90, 70, 50; C: 60, 60, 60), which plan does maximax choose?
Payoffs for three plans are A: 120, 80, 20; B: 90, 70, 50; C: 60, 60, 60. Which plan does the minimax regret rule choose?
The probabilities of a good, medium and poor market are 0.3, 0.5 and 0.2. Plan A pays 120, 80 and 20. What is the expected value of plan A?
The expected value with perfect information is 88 and the best expected value without it is 80. What is the value of perfect information?
What does sensitivity analysis show?
1. C, 2. A, 3. C, 4. A, 5. C, 6. D, 7. C, 8. B, 9. C, 10. D, 11. A, 12. A, 13. A, 14. D, 15. D, 16. C
Average contribution = (2 x 8 + 1 x 12) / 3 = $9.33. Break-even = 56,000 / 9.33.
Rank by contribution per unit of the scarce resource.
The optimum lies at a corner of the feasible region.
It shows the most worth paying for extra units.
-10 / 4 = -2.5, so demand is elastic.
At that quantity, the next unit adds as much to cost as to revenue.
MR = 100 - 0.04Q = 20, so Q = 2,000 and P = 100 - 40 = 60.
Skimming takes high margins from early buyers.
Minimum = marginal cost plus opportunity cost = 14 + 8.
Fixed costs that do not change are not relevant.
Maximin chooses the best of the worst outcomes: C gives 60.
Maximax picks the highest possible payoff, which is 120 for A.
The largest regrets are A 40, B 30 and C 60, so B has the smallest.
0.3 x 120 + 0.5 x 80 + 0.2 x 20 = 36 + 40 + 4 = 80.
88 - 80.
It tests the effect of changes in key variables.