  1. Demand is P = 80 - 0.01Q and marginal cost is $20. What is the profit-maximising quantity?

    • 1 4,000
    • 2 6,000
    • 3 3,000
    • 4 2,000
    جواب دیکھیں

    درست جواب: 3,000

    MR = 80 - 0.02Q = 20, so Q = 3,000.

    غلطی کی اطلاع دیں

  2. With the same demand equation (P = 80 - 0.01Q) and marginal cost of $20, what is the profit-maximising price?

    • 1 $20
    • 2 $60
    • 3 $50
    • 4 $80
    جواب دیکھیں

    درست جواب: $50

    P = 80 - 0.01 x 3,000 = 50.

    غلطی کی اطلاع دیں

  3. What is the main feature of green budgeting?

    • 1 It sets only financial targets
    • 2 It builds sustainability goals and targets into the budget
    • 3 It ignores the environment
    • 4 It removes all costs
    جواب دیکھیں

    درست جواب: It builds sustainability goals and targets into the budget

    For example, budgets are assigned to emissions reduction.

    غلطی کی اطلاع دیں

  4. Which budgeting approach is best suited to an uncertain and volatile environment?

    • 1 No budget
    • 2 Fixed annual budgeting
    • 3 Rolling budgeting
    • 4 Incremental budgeting only
    جواب دیکھیں

    درست جواب: Rolling budgeting

    Rolling budgets are updated regularly.

    غلطی کی اطلاع دیں

  5. What is the problem with setting a budget target that is too difficult?

    • 1 Managers may give up, so motivation falls
    • 2 Managers always work harder
    • 3 It has no effect
    • 4 Costs fall automatically
    جواب دیکھیں

    درست جواب: Managers may give up, so motivation falls

    Targets that are too easy also fail to motivate.

    غلطی کی اطلاع دیں

  6. Which principle says that managers should be judged only on what they can influence?

    • 1 Materiality
    • 2 Controllability
    • 3 Prudence
    • 4 Consistency
    جواب دیکھیں

    درست جواب: Controllability

    It protects motivation.

    غلطی کی اطلاع دیں

  7. What is a limitation of variance analysis?

    • 1 It uses future data
    • 2 It cannot be calculated
    • 3 It ignores non-financial and external factors
    • 4 It is too simple
    جواب دیکھیں

    درست جواب: It ignores non-financial and external factors

    Quality, customers, sustainability and competition are not captured.

    غلطی کی اطلاع دیں

  8. What is the purpose of a planning variance?

    • 1 To increase sales
    • 2 To reduce costs
    • 3 To separate the effect of changes in the standard that are outside the manager's control
    • 4 To measure efficiency only
    جواب دیکھیں

    درست جواب: To separate the effect of changes in the standard that are outside the manager's control

    The operational variance shows the manager's performance.

    غلطی کی اطلاع دیں