اردو

Home / Practice / ACCA / Performance Management / PM B Specialist cost and management accounting techniques

PM B Specialist cost and management accounting techniques

Written by Mahnoor Sheikh (ACCA)

9 ACCA Performance Management questions with answers and explanations.

Printable worksheet with answer key

All questions with answers
  1. Setup costs are $60,000 for 100 setups. A product needs 30 setups. What setup cost is charged to the product?

    • 1 $18,000
    • 2 $2,000
    • 3 $18
    • 4 $60,000
    Show answer

    Correct answer: $18,000

    Cost per setup = $600. 30 x $600 = $18,000.

    Report a mistake

  2. Which statement about ABC is correct?

    • 1 It ignores overheads
    • 2 It uses one overhead rate for the whole factory
    • 3 It is quicker and cheaper to set up than absorption costing
    • 4 It assigns overheads to products using the activities that cause the costs
    Show answer

    Correct answer: It assigns overheads to products using the activities that cause the costs

    ABC uses cost drivers for each cost pool.

    Report a mistake

  3. The market will pay $50 and the required margin is 20 percent of the selling price. What is the target cost?

    • 1 $30
    • 2 $10
    • 3 $40
    • 4 $60
    Show answer

    Correct answer: $40

    Target cost = price less the required profit = 50 - 10.

    Report a mistake

  4. Why does life-cycle costing matter for design decisions?

    • 1 It ignores costs after the sale
    • 2 Many of a product's costs are committed at the design stage
    • 3 It only measures production costs
    • 4 Design costs are not important
    Show answer

    Correct answer: Many of a product's costs are committed at the design stage

    Decisions made during design lock in most of the product's later costs.

    Report a mistake

  5. In throughput accounting, throughput is:

    • 1 Sales revenue less labour cost
    • 2 The number of units produced
    • 3 Sales revenue less all costs
    • 4 Sales revenue less direct material cost
    Show answer

    Correct answer: Sales revenue less direct material cost

    Labour and overheads are treated as fixed factory costs.

    Report a mistake

  6. A product earns a return per bottleneck hour of $50. The cost per factory hour is $30. What is the throughput accounting ratio?

    • 1 0.60
    • 2 1.67
    • 3 1.00
    • 4 20.00
    Show answer

    Correct answer: 1.67

    Ratio = return per factory hour / cost per factory hour = 50 / 30.

    Report a mistake

  7. A throughput accounting ratio below 1 for a product means that:

    • 1 The product earns less from the bottleneck than the cost of using it
    • 2 The product is the most profitable
    • 3 The product has no direct materials
    • 4 There is no bottleneck
    Show answer

    Correct answer: The product earns less from the bottleneck than the cost of using it

    A ratio below 1 is a warning sign.

    Report a mistake

  8. Which technique tracks the flow of materials and the cost of waste through a process?

    • 1 Flow cost accounting
    • 2 Zero-based budgeting
    • 3 Cost-plus pricing
    • 4 Target costing
    Show answer

    Correct answer: Flow cost accounting

    Flow cost accounting is an environmental management accounting technique.

    Report a mistake

  9. A cost driver is:

    • 1 The factor that causes the cost of an activity to change
    • 2 The total overhead cost
    • 3 The selling price
    • 4 The cost of direct materials
    Show answer

    Correct answer: The factor that causes the cost of an activity to change

    Examples are the number of setups or inspections.

    Report a mistake

More Performance Management topics