Home / NEBOSH IGC / Study books / Unit GIC1 / Element 3 / Page 11

Unit GIC1 · Element 3: Managing Risk: Understanding People and Process
3.4 Assessing Risk
Pages in this chapter (11 of 20)

The purpose of risk assessment and the "suitable and sufficient" standard

Risk assessments are an essential part of an OHS management system. They make a safer and healthier workplace possible, and in particular they help to:

A risk assessment must be suitable and sufficient. It should show that:

The detail should be proportionate to the risk and suited to the nature of the work. Insignificant risks can usually be ignored, as can risks from ordinary daily life, unless the work activity makes them worse or significantly changes them. The assessment should include only what you could reasonably be expected to know, since nobody is expected to foresee the unforeseeable.

A general approach: five steps

1Identify hazards2Identify people atrisk3Evaluate risk anddecide on controls4Record significantfindings5Review and update
Figure 3.8 The five steps of risk assessment

Step 1: identify hazards

Methods include:

Internal sourcesExternal sources
Self-inspection reportsNational legislation
Exposure monitoring resultsNational codes of practice and guidance notes
Medical records (suitably redacted to protect privacy)Health and safety regulators and enforcement agencies
Existing safety programmes (lockout/tagout, confined spaces, PPE and so on)Equipment and machinery operating manuals
Input from workersSafety data sheets (SDSs) from chemical manufacturers
Surveys or minutes of safety committee meetingsSafety and health experts and consultants
Results of job hazard or job safety analysesSeminars and workshops
Accident and absence recordsSafety journals and magazines
Equipment maintenance recordsBest practice from industry groups and trade associations
Training recordsTrade unions, local OSH committees and worker advocacy groups
Audit reports

Step 2: identify people at risk

For each hazard, think about how employees (including operators, cleaners and maintenance staff), contractors, visitors or members of the public might be harmed.

Some workers are more vulnerable and have particular needs, for example young workers, migrant workers, new or expectant mothers, lone workers and people with disabilities.

Step 3: assess the risks, taking account of what you already do, and decide whether you need to do more

Once hazards are identified, decide how likely it is that someone could be harmed and how serious the harm could be. This is assessing the level of risk. Decide:

Risk is the chance, high or low, that somebody could be harmed by the hazards found in Step 1, together with an indication of how serious the harm could be. A risk factor is something that can increase the chance of the hazard occurring. Judge both the likelihood of harm, such as an injury or illness, and its severity.

Each hazard should be studied to find its level of risk. Look at:

Also include the factors that contribute to the level of risk:

A common approach is to split risk into its two parts and rate each separately:

Likelihood1 Rare2 Unlikely3 Possible4 Likely5 Almostcertain5 Catastrophic5101520254 Major481216203 Moderate36912152 Minor2468101 Insignificant12345Severity1 to 2 low3 to 56 to 1112 to 1920 to 25 high
Figure 3.9 Illustrative 5 by 5 matrix; scores do not decide legal compliance

A matrix can help compare priorities, but its score does not determine legal compliance or give permission to continue unsafe work. The table below gives illustrative responses; apply hazard-specific guidance, mandatory controls and competent judgement regardless of the score. The summary notes group hazard/people identification together and risk assessment/control separately; this chapter groups the same actions differently within five steps.

LevelResponse
HighStop the process and implement controls
SignificantInvestigate the process and implement controls immediately
ModerateAssess whether effective interim controls allow safe work; otherwise pause affected work while controls are implemented
LowMaintain effective controls, complete further reasonably practicable improvements and monitor
After controlsReassess the remaining risk and verify effectiveness; residual risk is not a separate score band

The HSE website carries a lot of guidance on risk assessment.

Residual risk is the risk remaining after the controls being assessed are taken into account. It can still be unacceptable and require more action. Do not subtract risk-matrix scores as though they were precise physical quantities.

Tolerable risk does not mean acceptable. It describes an organisation's willingness to live with a risk in order to secure certain benefits, in the confidence that the risk is worth taking and is being properly controlled.

Look at what you already do and the controls already in place, and ask:

Page 11 of 20 in this chapter · page 21 of 39 in the book

Summary notes for Element 3 · Cheat sheet · Glossary. A study aid, not published or endorsed by NEBOSH.

Written by Imran Qureshi (NEBOSH)