NPVs of +$50,000 (p 0.3), +$20,000 (0.5) and -$40,000 (0.2) are expected. What is the expected NPV?
In the same project (NPVs of +$50,000, +$20,000 and -$40,000 with probabilities 0.3, 0.5 and 0.2), what is the probability of a negative NPV?
What does simulation do in investment appraisal?
Correct answer: Repeats the appraisal many times using random values for uncertain variables
It gives a distribution of NPVs.
Which is a disadvantage of simulation?
Correct answer: It needs probability distributions that may be hard to estimate
It is also costly and has no clear decision rule.
A risk-adjusted discount rate for a risky project is:
Correct answer: The cost of capital plus a premium
The premium is subjective.
Project A has NPV $30,000 for $100,000 and project B has NPV $25,000 for $50,000. What is the profitability index of B?
Project A has NPV $30,000 for $100,000 and project B has NPV $25,000 for $50,000. Both are divisible and $120,000 is available. What is the best total NPV?
For indivisible projects under capital rationing, how should they be compared?
Correct answer: By testing combinations of whole projects