45 defects are found in 5,000 units, each with 4 opportunities for a defect. The defects per million opportunities (DPMO) is:
Overall equipment effectiveness with availability of 90 percent, performance of 95 percent and quality of 98 percent is closest to:
The stages of the DMAIC cycle used in Six Sigma are:
Correct answer: Define, measure, analyse, improve and control
DMAIC is a structured approach to improving a process.
Kaizen costing and kaizen in general are based on:
Correct answer: Continuous small improvements by everyone
Kaizen drives a steady reduction in cost and waste.
Which of these is an internal failure cost in the costs of quality?
Correct answer: Cost of scrapping and reworking defective units found before delivery
Internal failure costs arise before delivery. External failure costs arise after.
Beyond budgeting suggests that organisations should:
Correct answer: Replace fixed annual budgets with rolling forecasts and relative performance targets
It aims to be more adaptive in a changing environment.
Business process re-engineering differs from continuous improvement because it:
Correct answer: Involves a radical redesign of a process