  1. Step one of the five step approach to risk assessment is to:

    • 1 Control the risks
    • 2 Record findings
    • 3 Identify the hazards and who is at risk
    • 4 Review the controls
    Show answer

    Correct answer: Identify the hazards and who is at risk

    The first step is hazard and people identification.

    Report a mistake

  2. The first and most effective item in the ISO 45001 hierarchy of control is to:

    • 1 Provide PPE
    • 2 Eliminate the hazard
    • 3 Use warning signs
    • 4 Train workers
    Show answer

    Correct answer: Eliminate the hazard

    Elimination is at the top, PPE at the bottom.

    Report a mistake

  3. A risk assessment that is 'suitable and sufficient' means it:

    • 1 Is completed once and never changed
    • 2 Deals with the significant risks in proportion to the level of risk
    • 3 Covers every possible hazard in great detail
    • 4 Is done by an outside consultant only
    Show answer

    Correct answer: Deals with the significant risks in proportion to the level of risk

    The standard is proportionate and focused on significant risks.

    Report a mistake

  4. Risk is:

    • 1 The result of a control measure
    • 2 The same as a hazard
    • 3 Anything with the potential to cause harm
    • 4 The likelihood of harm and its severity
    Show answer

    Correct answer: The likelihood of harm and its severity

    Risk combines likelihood and severity; the hazard is the potential for harm.

    Report a mistake

  5. A hazard is:

    • 1 Anything with the potential to cause harm
    • 2 A control measure
    • 3 The chance that harm will occur
    • 4 An injury that has happened
    Show answer

    Correct answer: Anything with the potential to cause harm

    Risk is the likelihood and severity of the harm.

    Report a mistake

  6. Risk profiling is:

    • 1 A list of injuries
    • 2 An audit of the policy
    • 3 A high-level ranking of activities and areas by risk
    • 4 A detailed study of one machine
    Show answer

    Correct answer: A high-level ranking of activities and areas by risk

    A risk assessment is the more detailed study.

    Report a mistake

  7. A risk assessment that is not suitable and sufficient is one that:

    • 1 Deals with the significant risks
    • 2 Is reviewed
    • 3 Considers who is at risk
    • 4 Misses significant hazards or is excessively detailed
    Show answer

    Correct answer: Misses significant hazards or is excessively detailed

    It should be proportionate to the level of risk.

    Report a mistake

  8. Which people should be identified in step one of the five step approach?

    • 1 Workers, contractors, visitors and the public who are at risk
    • 2 Only the person doing the assessment
    • 3 Only permanent staff
    • 4 Only the managers
    Show answer

    Correct answer: Workers, contractors, visitors and the public who are at risk

    Anyone who could be harmed should be considered.

    Report a mistake

  9. Step four of the five step approach is to:

    • 1 Identify the hazards
    • 2 Carry out the audit
    • 3 Record the findings
    • 4 Assess the risk
    Show answer

    Correct answer: Record the findings

    The five steps are identify, assess, control, record, review.

    Report a mistake

  10. Step five of the five step approach is to:

    • 1 Review the controls
    • 2 Control the risks
    • 3 Identify the hazards
    • 4 Record the findings
    Show answer

    Correct answer: Review the controls

    Reviews check the controls still work and update the assessment.

    Report a mistake

  11. In a risk assessment, existing controls should be:

    • 1 Removed
    • 2 Taken into account before deciding if more is needed
    • 3 Recorded only after the incident
    • 4 Ignored
    Show answer

    Correct answer: Taken into account before deciding if more is needed

    The study tip is to state existing controls first.

    Report a mistake

  12. The second item in the ISO 45001 hierarchy of control is:

    • 1 Use PPE
    • 2 Substitute with something less hazardous
    • 3 Provide training
    • 4 Eliminate the hazard
    Show answer

    Correct answer: Substitute with something less hazardous

    The order is eliminate, substitute, engineering and reorganisation, administrative, PPE.

    Report a mistake

  13. In the hierarchy of control, personal protective equipment is:

    • 1 The last item
    • 2 The second item
    • 3 The first item
    • 4 Not part of it
    Show answer

    Correct answer: The last item

    PPE depends on the user and is the last resort.

    Report a mistake

  14. Training is placed in the hierarchy under:

    • 1 Elimination
    • 2 Engineering controls
    • 3 Substitution
    • 4 Administrative controls
    Show answer

    Correct answer: Administrative controls

    Administrative controls include training and procedures.

    Report a mistake

  15. Residual risk is:

    • 1 The risk before any control
    • 2 The risk that remains after controls are in place
    • 3 The risk to visitors only
    • 4 The cost of the control
    Show answer

    Correct answer: The risk that remains after controls are in place

    It is compared with what is acceptable.

    Report a mistake