A project costs $1,000 at time 0 and gives inflows of $500, $600 and $700 in years 1 to 3. The reinvestment rate is 8 percent. The terminal value of the inflows at the end of year 3 is:
Correct answer: $1,931
500 x 1.08^2 + 600 x 1.08 + 700 = 583.2 + 648 + 700 = 1,931.2.
Using the terminal value of $1,931 and an outlay of $1,000, the modified internal rate of return over three years is closest to:
In adjusted present value, the base case NPV is calculated by discounting the project cash flows at:
Correct answer: The ungeared cost of equity
APV values the project as if all equity financed and adds the financing side effects such as the tax shield.
Under capital rationing, where projects are divisible and not repeatable, the correct approach is to rank projects by:
Correct answer: Profitability index (NPV per unit of capital)
Rank by NPV per $ of the limiting resource and accept in order until the capital is used up.
A real option to delay a project until more information is available is most like a:
Correct answer: Call option
Delay gives the right, but not the obligation, to invest later, and has value when there is uncertainty.
An option to abandon a project and sell the assets if it fails resembles a:
Correct answer: Put option
The right to sell at a known value gives downside protection.
A project's value is most sensitive to an input if:
Correct answer: A small change in that input produces a large change in NPV
Sensitivity analysis identifies the variables where a small error matters the most.